Investment in the Construction of Tien Lang Seaport and Logistics Center – Hai Phong
Location
-
Location: Vinh Quang Commune, Tien Lang District, Hai Phong City
Project Scale
-
Total land area: ~102 hectares
Total Investment Capital
-
Estimated total investment: VND 5.869 billion.
-
Site clearance compensation (land acquisition cost): ~ VND 990 billion.
Implementation Timeline
Project duration: 5 years from the date of investment approval.
Resettlement Impact & Solutions
-
Number of affected households requiring resettlement: approximately 700–800 households.
-
Proposed resettlement locations: Hung Thang New Urban Area and Tien Lang 1 Industrial Zone
Legal Considerations & Recommendations
- Port area: Detailed zoning plans for both land and water areas of the seaport must be approved.
- Depot/warehouse area: A 1/2000-scale subdivision planning must be approved.